Please note: This page was machine-translated. If anything is unclear, the German version is authoritative.
A transformer station that transfers electricity from the transmission system operator 50Hertz (380 kV) to the distribution system operator ENSO NETZ GmbH (110 kV).
From here, substations in the Elbe-Röder-Dreieck are supplied, feeding the medium-voltage grid and major industrial customers (including Wacker Chemie AG in Nünchritz and ESF Elbe-Stahlwerke Feralpi GmbH in Riesa).
The Streumen substation is of outstanding importance for the regional supply of electrical energy to industrial, commercial, and residential customers as well as generation plants in the district of Meissen (capacity at the site approx. 450 MW).
Construction period for the 50Hertz extra-high voltage facility: 2009–2011.